Focus: Tamworth

PO Box 18

South Tamworth, NH 03883



Home

Contact F:T

Join 
F: T

or send a message


Addresses


Hearings & meetings


F: T press releases

Latest release


F: T 
in the news

 HB90; 

Roll call votes in

House

Senate


Mission

Links


Hearings and meetings

PERMIT STATUS 


Wetlands dredge & fill (NH Department of Environmental Services)

Application submitted March 4, 2004; conditional permit issued July 29, 2004. Request for reconsideration (appeal) submitted August 18, 2004. 

On April 23, 2004 the Tamworth Conservation Commission submitted its recommendations on the application to DES. The committee examining the applications found many inadequacies. The DES hearing on April 27 was packed. Focus: Tamworth experts from Rath, Young & Pignatelli, Haley & Aldrich and Harris, Miller, Miller & Hanson submitted detailed analysis to the DES. 

In light of the passage of SB 458, the TCC submitted additional comments to the DES on May 11, 2004.

In early May, officials of DES and the US Army Corps of Engineers visited the site to do a new delineation of its wetlands. Additional wetlands were identified.

In a letter dated May 21, NH DES asked CMI to submit more information and change its track design. See press release and  the DES request letter for details. CMI re-submitted its application early in July. 

On July 29, DES issued a permit with 36 conditions. On August 18, a group of more than 30 Tamworth property owners appealed this permit decision. At a hearing on April 12, 2005, the NH Wetlands Council declined to accept the appeal.


Site specific (NH DES)

Application submitted March 16, 2004; permit issued with conditions September 20, 2004. 


Section 404 (US Army Corps of Engineers)

Application submitted March 4, 2004

ACOE "noticed" the CMI application July 13, 2004. The comment period was extended to October 16, 2004. ACoE held a hearing on October 6, 2004 in Tamworth. At the end of January, 2005 ACoE hired a noise expert to analyze two conflicting noise studies. The analysis will take "several weeks." The U.S. Environmental Protection Agency is also involved. 

Permit issued August 2005. 

Focus: Tamworth sent a letter to ACOE official Mike Hicks requesting reconsideration, based on information from the ACOE noise expert obtained by F:T under the Freedom of Information Act. Mr. Hicks declined to reconsider; a challenge to the permit was filed in U.S. District Court October 9. 


Section 401 water quality certificate (DES)

Application submitted March 4, 2004; permit issued with conditions March 22, 2005. 
Appeal filed by St. Andrew's-in-the-Valley Episcopal Church and more than forty other abutters and Tamworth residents on April 22. See press release.
This appeal was settled when CMI agreed to redesign its fuel-handling plans and made several other concessions.


Tamworth Wetlands Ordinance 

Application for a special use permit submitted June 21, 2004. Application withdrawn August 23, 2004

A July 21 hearing by the Tamworth Planning Board, which is responsible for issuing the Special Use Permit (SUP), was continued to August 25th to allow notices to go out to other towns in the region. The August hearing was held, but the only action was to read a letter from CMI withdrawing its application. About 125 people attended. Click here for the text of the ordinance.

A December, 2005 court order ruled that the CMI needs an SUP to start construction. 

New application for an SUP submitted on August 3, 2006. 

The planning board began the consideration process on August 23. A public hearing was held October 17, and will be continued at the next Planning Board meeting October 25. Press release.


Tamworth hazardous waste ordinance

Application not submitted. Does not apply per December 2005 summary judgment. 


NH DOT access to Rt 25

Obtained


Other permits:

  • Storm water - construction general permit

  • Water supply engineering permit

  • Large ground water withdrawal permit

  • Groundwater discharge permit

  • Underground or aboveground storage tank facility permit

  • Tamworth subdivision permit

  • Tamworth race track operations permit (if RSA 287-G is repealed)

  • Additional permits under the EPA Clean Air Act and NH dams regulations

 

Last update: November 8, 2006

Site hosted by Beverly Woods Web Services